Right is Right and Wrong is Wrong

Editorials

Blatant Fargo ND Land Grab of the Last Natural Flood Plain Adjacent to the City
Commentary on the highlighted article below:

The Corps’ lawyers “specifically deny any allegations that the Corps violated any Federal law or policy in the planning process in calculating the benefit-cost ratio or otherwise.”

We can get into a mind numbing legal argument over that –that is for lawyers. For the rest of us, few would argue that the south Fargo flood plain is Fargo’s future development area. (See Fargo 2007 TIER 2 growth plan and the Corps own documents.)

The cost benefit is in large part based on the reduced cost, saving of development cost by removing regulatory flood plain controls.

“…$10.4 million average annual benefits for the ND diversion”. Appendix C 3.7.5 (read original).

This is calculated for the future growth area. The benefits are based on a speculated level of future growth.

“Errors do not cease to be errors simply because they’re ratified into law.“ – E.A. Bucchianeri

Read More or Add Your Comment on: Save The Farm Facebook Page

Lawyers for Corps reject claims in suit against F-M diversion
By: Erik Burgess, INFORUM

FARGO – Lawyers for the U.S. Army Corps of Engineers are denying several allegations made in a lawsuit against the proposed Fargo-Moorhead flood diversion project.

The 35-page response to the lawsuit was filed Monday, and in it, the government’s legal team rejects the claim from diversion opponents that the purpose of the $1.8 billion flood control project is to protect developable land immediately south of Fargo.Lawyers for the corps also deny the suit’s claim that the diversion and proposed ring levee around Oxbow, Hickson and Bakke will cause “irreparable harm” to the cities and other entities represented by the Richland-Wilkin Joint Powers Authority, which filed the suit in August.

The lawsuit accuses diversion leaders of unnecessarily expanding the scope of the flood protection project, damaging farmland in the so-called “staging area,” where water would be stored in the event of a severe flood before moving through the diversion channel.

In the suit, diversion opponents argue that Fargo and Cass County favor the proposed diversion project because it would protect “large portions of Fargo’s undeveloped flood plain.” The suit alleges that the local project sponsors and the corps developed ways to “skew the cost-benefit analysis in ways which overstate the benefits … and understate the costs” of the proposed project.

In their response, the corps’ lawyers said they “specifically deny any allegations that the Corps violated any Federal law or policy in the planning process in calculating the benefit-cost ratio or otherwise.”

The suit also alleges that the diversion will cause “unnecessary repeated intentional flooding of large expanses” of both Richland and Wilkin counties, and that the corps only considered one flood storage option.

In their response, lawyers for the Corps said the staging area only includes 788 acres and two residential structures in Richland County and 450 acres and one residential structure in Wilkin County.

Corps’ lawyers argue that other options for upstream staging were studied.

“But (they) were rejected, among other reasons, because of their greater impacts to people, property, agriculture, and the environment,” the response says.

In the suit, diversion opponents further argue against the proposed ring dike for the Oxbow, Hickson and Bakke area south of Fargo, saying that the levee will have “major environmental impacts” and would be a “monumental waste of taxpayer money” if the full diversion isn’t built.

“The purpose of these ring-dikes would be to provide protection against artificially created flooding caused by the dam downstream,” the suit says.

Corps’ lawyers argue that Oxbow “routinely experiences flooding under existing conditions,” and that a historic event would flood Bakke and Hickson, and so the three would benefit from a ring dike.

The lawyers argue further that the $65 million ring dike is a cheaper protection plan compared to the $74 million price tag for buying out the three communities.

Work on the ring levee is slated to start next year with home acquisitions. The levee could be completed by 2016.

A federal water bill authorizing the diversion has been approved individually by the U.S. Senate and House, and the two chambers are now in conference committee to hash out the differences and pass one final bill. If authorized, the diversion would still need appropriation of federal funds.

 

Views: 174

2 thoughts on “Right is Right and Wrong is Wrong

  1. Hopefully the federal judge handling this case is not totally naïve to the project, looking at it through the narrow tunnel (vision) that Goliath (Diversion Authority, USACE)are. We need him to make a stand against “GREED”. It’s the right thing to do…

  2. I cant wait for the response that was promised me about the ring dike around the community. approximately 600 acres will be inside the ring with about 10 acre feet of rain water storage included. When I asked where the other 300 acre feet of water would be stored if we got a 6″ rain, I was told, “We will get back to you, We will fix that during the design”. I am still waiting, and the first shovel of dirt is scheduled to be moved in 4 months. Seems like a detail like that would need to be designed in before the digging starts…..

Leave a Reply

Your email address will not be published.

This site uses Akismet to reduce spam. Learn how your comment data is processed.