Fargo Dam and Diversion Costs as of January 31st, 2015

Fargo Dam and Diversion Costs as of January 31st, 2015

Fargo Diversion Authority spent another $11,903,574.06 from December 31st, 2014 to January 31st, 2015. Nearly 1/13 ( 7% ) of the original projected cost and they haven’t even started on the actual main project.

Fargo Dam and Diversion Costs as of November 30th, 2014

Fargo Dam and Diversion Costs as of November 30th, 2014

Fargo Diversion Authority spent another $17,623,733.09 from October 31st to November 30th, 2014. Nearly 1/15 (6.4%) of the original projected cost and they haven’t even started on the actual main project. The bulk of the costs went towards the OHB ring-dike-levee and new golf course features…, instead of completing crucial internal flood protection for the city of Fargo and it’s residents. When the state of North Dakota committed monies to Fargo, did they ever think it would be spent outside the jurisdictional boundaries of Fargo?

Fargo Dam and Diversion Costs as of October 31st, 2014

Fargo Dam and Diversion Costs as of October 31st, 2014

Fargo Diversion Authority spent $13,316,244.27 from September 30th to October 31st, 2014. Nearly 1/18 (5.5%) of the original projected cost and they haven’t even started on the actual main project. The bulk of the costs went towards the OHB ring-dike-levee and new golf course features…, instead of completing crucial internal flood protection for the city of Fargo and it’s residents. When the state of North Dakota committed monies to Fargo, did they ever think it would be spent outside the jurisdictional boundaries of Fargo?

Fargo Dam and Diversion Costs as of August 31st, 2014

Fargo Dam and Diversion Costs as of August 31st, 2014

Fargo Diversion Authority spending spree: $1.9 million increase in one month from July 31st, 2014 to August 31st, 2014.

Fargo Dam and Diversion Costs as of July 31st, 2014

Fargo Dam and Diversion Costs as of July 31st, 2014

Fargo Diversion Authority spending spree: $16.4 million increase in one month from June 30th, 2014 to July 31st, 2014.

Fargo Dam and Diversion Costs as of June 30th, 2014

Fargo Dam and Diversion Costs as of June 30th, 2014

Fargo Dam and Diversion Costs as of June 30th, 2014   Vendor Name Approved Contract/Invoice Amount Liquidated Outstanding Encumbrance HOUSTON-MOORE GROUP LLC 19,890,094.00 13,119,239.51 6,770,854.49 CH2M HILL ENGINEERS INC 12,491,244.99 11,920,819.01 570,425.98 CASS COUNTY JOINT WATER RESOUR 9,167,398.87 9,167,398.87 – COMMERCIAL TITLE LLC 3,869,541.00 3,869,541.00 – TITLE COMPANY 3,641,500.00 3,641,500.00 – OXBOW. CITY OF 2,935,741.87 […]

Moorhead Rejects Fargo Diversion Authority Right of Entry

Moorhead Rejects Fargo Diversion Authority Right of Entry

Moorhead residents should consider themselves lucky have a city council that is still willing to weigh the pro’s and con’s of an issue, rather than otto-matically rubber stamping Fargo Diversion Authority propaganda.