Fargo Dam and Diversion Costs as of December 31, 2015

Fargo Diversion Authority spent another $ 14,937,811.26 from November 30 to December 31, 2015. 1/6th (14.64% ) of the original projected cost and they haven’t even started on the actual main project. The Fargo Diversion Authority has pumped over $61.1 million into OHB ring-dike-levee and private country club, which provides ZERO FLOOD PROTECTION BENEFIT TO FARGO.

Continue Reading

Fargo Dam and Diversion Costs as of November 30, 2015

Fargo Diversion Authority spent another $ 8,572,964.97 from October 31 to November 30, 2015. 1/7th (13.8% ) of the original projected cost and they haven’t even started on the actual main project. The Fargo Diversion Authority has pumped over $59 million into OHB ring-dike-levee, which provides ZERO FLOOD PROTECTION BENEFIT TO FARGO.

Continue Reading

Whitney’s Witless Water Whining

Think about this…, the Fargo Dam and FM Diversion Authority and the USACE intentionally downgraded the 2009 flood crisis to a 50 year flood event, which would make a 100 year flood event seem even more dangerous and unrealistic, then project proponents try to invent a theoretical “what if” crisis 5 times larger than the 100 year flood event they claim has not yet occurred to justify their agenda.

Continue Reading

Fargo Dam and Diversion Costs as of October 31, 2015

Fargo Diversion Authority spent another $ 7,530,334.43 from September 30 to October 31, 2015. 1/7th (13.32% ) of the original projected cost and they haven’t even started on the actual main project. The Fargo Diversion Authority has pumped over $59 million into OHB ring-dike-levee, which provides ZERO FLOOD PROTECTION BENEFIT TO FARGO.

Continue Reading