Fargo Dam and Diversion Costs as of August 31st, 2014
Vendor Name | Approved Contract/Invoice Amount |
Liquidated | Outstanding Encumbrance |
HOUSTON-MOORE GROUP LLC | 21,689,077.45 | 14,354,260.77 | 7,334,816.68 |
CASS COUNTY JOINT WATER RESOURCE | 14,341,563.69 | 10,566,904.46 | 3,774,659.23 |
OXBOW. CITY OF | 13,672,412.68 | 3,674,846.50 | 10,004,649.51 |
CH2M HILL ENGINEERS INC | 12,280,819.01 | 12,100,819.01 | 180,000.00 |
COMMERCIAL TITLE LLC | 3,869,541.00 | 3,869,541.00 | – |
TITLE COMPANY | 3,641,500.00 | 3,641,500.00 | – |
ARMY CORP OF ENGINEERS | 2,450,000.00 | 1,925,000.00 | 525,000.00 |
KENNELLY & OKEEFFE | 1,729,310.56 | 1,729,310.56 | – |
URS CORPORATION | 1,501,488.42 | 886,790.84 | 614,697.58 |
MINNESOTA DNR | 1,492,718.00 | 944,770.00 | 547,948.00 |
DORSEY & WHITNEY LLP | 1,188,239.62 | 1,188,239.62 | – |
MOORE ENGINEERING INC | 662,468.17 | 662,468.17 | – |
DUCKS UNLIMITED | 587,180.00 | 587,180.00 | – |
HOUSTON ENGINEERING INC | 576,669.57 | 576,669.57 | – |
RED RIVER BASIN COMMISSION | 500,000.00 | 447,747.40 | 52,252.60 |
NORTHERN TITLE CO | 484,016.00 | 484,016.00 | – |
CASS COUNTY TREASURER | 182,125.46 | 182,125.46 | – |
ERIK R JOHNSON & ASSOCIATES | 179,890.20 | 179,890.20 | – |
PFM PUBLIC FINANCIAL MANAGEMEN | 146,460.00 | 146,460.00 | – |
PROSOURCE TECHNOLOGIES, INC | 100,000.00 | 8,324.94 | 91,675.06 |
ULTEIG ENGINEERS INC | 100,000.00 | 0.00 | 100,000.00 |
BRAUN INTERTEC CORP | 90,210.00 | 77,629.00 | 12,581.00 |
OHNSTAD TWICHELL PC | 58,730.66 | 58,730.66 | – |
IN SITU ENGINEERING | 54,800.00 | 47,973.00 | 6,827.00 |
ADVANCED ENGINEERING INC | 50,000.00 | 50,000.00 | – |
US GEOLOGICAL SURVEY | 46,920.00 | 46,920.00 | – |
GEOKONINC | 33,815.36 | 33,815.36 | – |
COLDWELL BANKER | 33,066.02 | 33,066.02 | – | NIXON PEABODY LLC | 30,000.00 | – | 30,000.00 |
INNOVATIVE ABSTRACT & TITLE CO | 15,921.53 | 15,921.53 | – |
CITY OF FARGO | 15,380.00 | 15,380.00 | – |
MOORHEAD. CITY OF | 15,062.90 | 15,062.90 | – |
WARNER&CO | 14,925.00 | 14,925.00 | – |
BRIGGS & MORGAN PA | 12,727.56 | 12,727.56 | – |
GRAY PANNELL & WOODWARD LLP | 10,000.00 | 10,000.00 | – |
MCKINZIE METRO APPRAISAL | 3,200.00 | 3,200.00 | – |
FORUM COMMUNICATIONS (LEGALS) | 2,224.20 | 2,224.20 | – |
DAWSON INSURANCE AGENCY | 1,867.81 | 1,867.81 | – |
FORUM COMMUNICATIONS (ADVERT) | 1,743.77 | 1,743.77 | – |
CLAY COUNTY AUDITOR | 1,550.00 | 1,550.00 | – |
SEIGEL COMMUNICATIONS SERVICE | 1,490.00 | 1,490.00 | – |
RED RIVER TITLE SERVICES INC | 1,305.00 | 1,305.00 | – |
HUBER,STEVE | 1,056.43 | 1,056.43 | – |
NORTH DAKOTA TELEPHONE CO | 926.40 | 868.40 | 58.00 |
TRIO ENVIRONMENTAL CONSULTING | 747.60 | 747.60 | – |
RED RIVER VALLEY COOPERATIVE A | 536.96 | 536.96 | – |
FERRELLGAS | 496.00 | 496.00 | – |
BROKERAGE PRINTING | 473.33 | 473.33 | – |
GALLAGHER BENEFIT SERVICES INC | 250.00 | 250.00 | – |
DONS PLUMBING | 240.00 | 240.00 | – |
KOCHMANN, CARTER | 210.00 | 105.00 | 105.00 |
CURTS LOCK & KEY SERVICE INC | 138.10 | 138.10 | – |
GOOGLE LOVEINTHEOVEN | 116.00 | 116.00 | – |
FEDERAL EXPRESS CORPORATION | 71.89 | 71.89 | – |
CASS COUNTY RECORDER | 68.00 | 68.00 | – |
Grand Total: August 30th, 2014 | 81,882,833.68 | 58,607,564.02 | 23,275,269.22 |
Last Month: July 31st, 2014 | 79,934,616.80 | ||
One Month Increase | 1,948,216.88 |
PDF – Cumulative Vendor Payments Detail Fargo Dam and FM Diversion as of August 31st, 2014
Views: 75