CASE 0:13-cv-02262-JRT-LIB Document 80

Initial authorization is not the final word on a Corps project. Authorized projects may be modified for a number of reasons including cost changes and design modifications. The Corps may not commence construction on a significant flood control project without both Congressional authorization and a Congressional appropriation(s). Congressional authorization of a flood control project does not guarantee federal funding through a Congressional appropriation.

Continue Reading

CASE 0:13-cv-02262-JRT-LIB Document 79

Nathan J. Hartshorn, MN Assistant Attorney General: The Project would flood thousands of acres of Minnesota farmland in order to expand development opportunities in the Fargo-Moorhead Metropolitan Area. The Project also would require construction of a high-hazard dam on the Red River, upstream of Minnesota communities. This high hazard dam requires MDNR dam safety and work in public waters permits, and triggered a mandatory Environmental Impact Statement (EIS) under Minnesota law.

Continue Reading