Defending Richland and Wilkin counties July 16th, 2015

Defending Richland and Wilkin counties July 16th, 2015

So many questions, too few answers…, taxpayer subsidized buyouts to mitigate a project that does not have federal funding or turned a shovel of dirt for the diversion channel.

Fargo Dam and Diversion Costs as of June 30th, 2015

Fargo Dam and Diversion Costs as of June 30th, 2015

Fargo Diversion Authority spent another $ 7,415,358.87 from May 31st to June 30th, 2015. 1/9th (11.11% ) of the original projected cost and they haven’t even started on the actual main project.

OHB Design Flaw Negates Stated Flood Protection

OHB Design Flaw Negates Stated Flood Protection

OHB project area contains a design feature one foot lower, capable of filling the entire OHB area to the top of the levee within 4.5 hours.

Fargo Dam and Diversion Costs as of May 31st, 2015

Fargo Dam and Diversion Costs as of May 31st, 2015

Fargo Diversion Authority spent another $22,456,624.30 from April 30th to May 31st, 2015. Nearly 1/9 (10.69% ) of the original projected cost and they haven’t even started on the actual main project.

Fargo Dam and Diversion Costs as of April 30th, 2015

Fargo Dam and Diversion Costs as of April 30th, 2015

Fargo Diversion Authority spent another $7,269,195.32 from March 31st to April 30th, 2015. Nearly 1/10 ( 9.84 % ) of the original projected cost and they haven’t even started on the actual main project.

Angry Rodger Olson Bullies Clay Commissioner

Angry Rodger Olson Bullies Clay Commissioner

Perhaps it’s just a feeble attempt at misdirection in hopes of duping some unwitting souls into believing that he does not have that stank of Fargo/Cass imperialism on his breath…, or not?

Fargo Dam and Diversion Costs as of March 31st, 2015

Fargo Dam and Diversion Costs as of March 31st, 2015

Fargo Diversion Authority spent another $5,144,824.87 from February 28th to March 31st, 2015. Nearly 1/11 ( 9.44 % ) of the original projected cost and they haven’t even started on the actual main project.

Fargo Dam and Diversion Costs as of February 28th, 2015

Fargo Dam and Diversion Costs as of February 28th, 2015

Fargo Diversion Authority spent another $32,584,755.14 from January 31st to February 28th, 2015. Nearly 1/11 ( 9.2 % ) of the original projected cost and they haven’t even started on the actual main project.

Fargo Dam and Diversion Costs as of January 31st, 2015

Fargo Dam and Diversion Costs as of January 31st, 2015

Fargo Diversion Authority spent another $11,903,574.06 from December 31st, 2014 to January 31st, 2015. Nearly 1/13 ( 7% ) of the original projected cost and they haven’t even started on the actual main project.

Fargo Dam and Diversion Costs as of November 30th, 2014

Fargo Dam and Diversion Costs as of November 30th, 2014

Fargo Diversion Authority spent another $17,623,733.09 from October 31st to November 30th, 2014. Nearly 1/15 (6.4%) of the original projected cost and they haven’t even started on the actual main project. The bulk of the costs went towards the OHB ring-dike-levee and new golf course features…, instead of completing crucial internal flood protection for the city of Fargo and it’s residents. When the state of North Dakota committed monies to Fargo, did they ever think it would be spent outside the jurisdictional boundaries of Fargo?