FM Diversion and Dam Increases national debt

Archive for U.S. Army Corps of Engineers

You are browsing the archives of U.S. Army Corps of Engineers.

Fargo Dam and Diversion Costs as of December 31, 2015

Fargo Dam and Diversion Costs as of December 31, 2015

Fargo Diversion Authority spent another $ 14,937,811.26 from November 30 to December 31, 2015. 1/6th (14.64% ) of the original projected cost and they haven’t even started on the actual main project. The Fargo Diversion Authority has pumped over $61.1 million into OHB ring-dike-levee and private country club, which provides ZERO FLOOD PROTECTION BENEFIT TO FARGO.

Fargo Dam and Diversion Costs as of November 30, 2015

Fargo Dam and Diversion Costs as of November 30, 2015

Fargo Diversion Authority spent another $ 8,572,964.97 from October 31 to November 30, 2015. 1/7th (13.8% ) of the original projected cost and they haven’t even started on the actual main project. The Fargo Diversion Authority has pumped over $59 million into OHB ring-dike-levee, which provides ZERO FLOOD PROTECTION BENEFIT TO FARGO.

Fargo Dam and Diversion Costs as of October 31, 2015

Fargo Dam and Diversion Costs as of October 31, 2015

Fargo Diversion Authority spent another $ 7,530,334.43 from September 30 to October 31, 2015. 1/7th (13.32% ) of the original projected cost and they haven’t even started on the actual main project. The Fargo Diversion Authority has pumped over $59 million into OHB ring-dike-levee, which provides ZERO FLOOD PROTECTION BENEFIT TO FARGO.

Fargo Dam and Diversion Costs as of September 30, 2015

Fargo Dam and Diversion Costs as of September 30, 2015

Fargo Diversion Authority spent another $ 4,793,218.74 from August 31 to September 30, 2015. 1/8th (12.9% ) of the original projected cost and they haven’t even started on the actual main project. The Fargo Diversion Authority has pumped over $59 million into OHB ring-dike-levee, which provides ZERO FLOOD PROTECTION BENEFIT TO FARGO.

Fargo Dam and Diversion Costs as of August 31st, 2015

Fargo Dam and Diversion Costs as of August 31st, 2015

Fargo Diversion Authority spent another $ 24,218,927.98 from July 31st to August 31st, 2015. 1/8th (12.63% ) of the original projected cost and they haven’t even started on the actual main project. The Fargo Diversion Authority has pumped over $55 million into OHB ring-dike-levee, which provides ZERO FLOOD PROTECTION BENEFIT TO FARGO.

Fargo Dam and Diversion Costs as of July 31st, 2015

Fargo Dam and Diversion Costs as of July 31st, 2015

Fargo Diversion Authority spent another $ 3,155,560.11 from June 30th to July 31st, 2015. 1/9th (11.28% ) of the original projected cost and they haven’t even started on the actual main project.

Situational Ethics Part 7

Situational Ethics Part 7

So if the project is truly “mitigation”…, why did Mr. Nyhof “flip” and become a cheerleader of the project that created the impacts requiring said mitigation? Mr. Nyhof could have easily remained opposed, that is, if that was his genuine position in the beginning.

Situational Ethics Part 6

Situational Ethics Part 6

After reading Mr. Nyhof’s letter to Terry Birkenstock (USACE) several times, I cannot not find any word or phrase, specifically requesting his city be saved.

Situational Ethics Part 2

Situational Ethics Part 2

Not only did Oxbow, ND exceed the FEMA and USACE 100 year flood stream-flows in 2009…, it exceeded the FEMA 500 year flood level as well.

Fargo Dam and Diversion Costs as of June 30th, 2015

Fargo Dam and Diversion Costs as of June 30th, 2015

Fargo Diversion Authority spent another $ 7,415,358.87 from May 31st to June 30th, 2015. 1/9th (11.11% ) of the original projected cost and they haven’t even started on the actual main project.