FM Diversion and Dam Increases national debt

admin

You are browsing the archives of admin.

Fargo Dam and Diversion Costs as of October 31, 2015

Fargo Dam and Diversion Costs as of October 31, 2015

Fargo Diversion Authority spent another $ 7,530,334.43 from September 30 to October 31, 2015. 1/7th (13.32% ) of the original projected cost and they haven’t even started on the actual main project. The Fargo Diversion Authority has pumped over $59 million into OHB ring-dike-levee, which provides ZERO FLOOD PROTECTION BENEFIT TO FARGO.

ND Senator Larry Luick Comments to MN DNR

ND Senator Larry Luick Comments to MN DNR

With the condition of completion of the levees in Fargo, we do have time to put together a better plan that has benefits for more people, communities, and property. We also can meld together the natural resource benefits attributable to better soil and water management practices.

‘Upstream’ comment not true

‘Upstream’ comment not true

None of us chose where the city of Fargo was established or where the flood plain extends. It is, however, our responsibility to plan and act accordingly as to what our choices are today.

Fargo Dam and Diversion Costs as of September 30, 2015

Fargo Dam and Diversion Costs as of September 30, 2015

Fargo Diversion Authority spent another $ 4,793,218.74 from August 31 to September 30, 2015. 1/8th (12.9% ) of the original projected cost and they haven’t even started on the actual main project. The Fargo Diversion Authority has pumped over $59 million into OHB ring-dike-levee, which provides ZERO FLOOD PROTECTION BENEFIT TO FARGO.

Minnesota DNR Seeks Comments on Fargo Dam and FM Diversion Project

Minnesota DNR Seeks Comments on Fargo Dam and FM Diversion Project

The MN DNR will also be hosting an open house and informational meeting to further explain the process: October 14, 2015 (5p-10p) Marriott Courtyard, Moorhead, MN.

Fargo Dam and Diversion Costs as of August 31st, 2015

Fargo Dam and Diversion Costs as of August 31st, 2015

Fargo Diversion Authority spent another $ 24,218,927.98 from July 31st to August 31st, 2015. 1/8th (12.63% ) of the original projected cost and they haven’t even started on the actual main project. The Fargo Diversion Authority has pumped over $55 million into OHB ring-dike-levee, which provides ZERO FLOOD PROTECTION BENEFIT TO FARGO.

Fargo Dam and Diversion Costs as of July 31st, 2015

Fargo Dam and Diversion Costs as of July 31st, 2015

Fargo Diversion Authority spent another $ 3,155,560.11 from June 30th to July 31st, 2015. 1/9th (11.28% ) of the original projected cost and they haven’t even started on the actual main project.

Case Civil No. 13-2262 (D287) | US District Court, District of  Minnesota

Case Civil No. 13-2262 (D287) | US District Court, District of Minnesota

The following clarification was received late today from US District Court, District of Minnesota. Summmary: Home and golf course construction may continue, however, the all physical construction activities related to the OHB ring levee, if ongoing, must cease immediately. [Jump to Judges Decision and Order Decision] CASE 0:13-cv-02262-JRT-LIB Document 287 Filed 07/28/15 UNITED STATES DISTRICT […]

Defending Richland and Wilkin counties July 16th, 2015

Defending Richland and Wilkin counties July 16th, 2015

So many questions, too few answers…, taxpayer subsidized buyouts to mitigate a project that does not have federal funding or turned a shovel of dirt for the diversion channel.

Fargo Dam and Diversion Costs as of June 30th, 2015

Fargo Dam and Diversion Costs as of June 30th, 2015

Fargo Diversion Authority spent another $ 7,415,358.87 from May 31st to June 30th, 2015. 1/9th (11.11% ) of the original projected cost and they haven’t even started on the actual main project.